It's hard to see how LRT will be ready by Canada Day

This was posted more than 12 months ago. The information may be outdated.

By Joanne Chianello, CBC News Ottawa, June 3, 2019

At last count — we're on unofficial deadline No. 4 now, in case you've lost track — the consortium building the LRT was supposed to hand it over by the end of this month.

But considering some trains still have defects, there are issues with the rail switches and the 12-day consecutive testing hasn't even begun, it's hard to see how Rideau Transit Group (RTG) can hand over the $2.1-billion Confederation Line by June 30.