Water line replacement on Centre Street – Construction starting August 13

By The Review, August 14, 2018

On August 13, construction began on Centre Street in Alexandria, between Main Street South and Bishop Street South to replace a water main. Work crews will be replacing the four-inch iron main with a new six-inch PVC pipe. This will improve the quality and quantity of water for residents served by this main.

Crews will be constructing a temporary overland water main which will be installed during the week of August 13. Construction of the new water line is expected to begin on August 20.

In order to minimize water pressure losses, Water Works staff may be required to enter local residences to hook up a temporary service. The entire project is expected to take five weeks.

https://thereview.ca/2018/08/14/water-line-replacement-on-centre-street-construction-starting-august-13/

Connect with us