By Matthew Pearson, Ottawa Citizen, June 16, 2017
Ottawa’s LRT builder has nearly reached the half-way mark of its busiest year of construction.Work by the Rideau Transit Group is underway at all 13 Confederation LRT Line stations and the 12.5-kilometre rail line that connects them.
Close to nine kilometres of track in either direction has either been laid or is in the process of being laid along the mainline and more than one-third of the overhead wires used to power the trains have been installed. Thirteen Alstom Citadis light rail vehicles are fully assembled (of the total 34).